M6 motorway to Korat opens free, 24 hours a day, from 25 December
Weekend-only trial ends; tolls planned after the free period, from April 2027
The M6 motorway between Bang Pa-in and Nakhon Ratchasima (Korat) opens along its full 196 km from Friday 25 December 2026, in both directions, 24 hours a day and free of charge. Deputy Prime Minister and Transport Minister Phiphat Ratchakitprakarn confirmed the date at a briefing on 4 November, timed for the New Year 2027 holiday getaway.
The free period is a trial run before full service. The Department of Highways plans to start collecting tolls in April 2027.
At a glance
- Road: Motorway 6 (M6), Bang Pa-in to Nakhon Ratchasima, 196 km
- From: 25 December 2026, every day, 24 hours, both directions
- Cost: free during the trial; tolls planned from April 2027, rates to be announced
- Speed: no more than 80 km/h during the trial, the minister said in October
- Help: Department of Highways hotline 1586, then press 6 (free, 24 hours)
What changes on 25 December
Since 21 August, the motorway has opened only at weekends, from Friday at 12:00 to Sunday at 24:00. That trial covers the 110 km from Bang Pa-in to Pak Chong, with entry at Bang Pa-in, Hin Kong, Kaeng Khoi, Muak Lek and Pak Chong, and links to the section from Pak Chong to Nakhon Ratchasima that was already open. Only four-wheel cars are allowed.
From 25 December, the whole route opens every day. The ministry says it gives drivers heading to the northeast an alternative to Phahonyothin Road and Mittraphap Road, which carry most holiday traffic out of Bangkok. According to the Department of Highways, civil works are 99.81% complete and operating systems 96.42%.
Which vehicle types may use the road from 25 December is to be announced. Parts of the project are still being finished, so the minister set the 80 km/h limit for safety; a later rise to 120 km/h will be considered.
M6 motorway toll and rest stops
Toll rates have not been officially announced. The Department of Highways says collection will begin in April 2027, after the trial.
During the weekend trial, drivers can stop at two temporary rest areas, Thap Kwang and Si Khio. Fifteen permanent service areas are planned along the route under a public-private partnership; the department expects to sign the contract around February 2027 and to open them within two years.
Other roads opening for New Year
The 24.7 km M82 motorway from Rama 2 to Ban Phaeo is already open free, 24 hours a day, on trial. Its Ban Phaeo exit narrows from three lanes to one, and the Department of Highways has been told to widen it to two.
The Expressway Authority of Thailand plans a trial opening in December of the elevated section of the Rama 3 to Dao Khanong to Outer Ring Road expressway above Rama 2 Road; the exact date is to be announced.
Planning the trip
Check the Department of Highways for road notices before setting off. If Korat is the destination, our Korat Zoo guide covers tickets, shows and opening hours. Going by rail instead? See the SRT New Year special trains. More updates are in latest.
Sources
- Thai Post: Phiphat speeds up expressway and motorway openings for New Year 2027, M6 free along the full route from 25 December (5 November 2026)
- Post Today: M6 free along the full route from 25 December, M82 bottleneck to be fixed (5 November 2026)
- The Nation: Thailand to open 196km M6 toll-free from December 25 (7 November 2026)
- Daily News: Phiphat confirms M6 opens free along all 196 km, 24 hours, from 25 December (21 October 2026)
- Daily News: M6 opens on weekends from 21 August, every day from 25 December (19 August 2026)
- Bangkok Biz News: M6 opens free at five entry points, tolls from April next year